Judgment of 26 September 2018, Case No 30 Cdo 2503/2016 – International jurisdiction
Article 5 (1) Brussels I Regulation, International jurisdiction of a court
Judgment of the Supreme Court of 26 September 2018, Case No 30 Cdo 2503/2016
(Article 5 (1) Brussels I Regulation, International jurisdiction of a court)
The applicants (domiciled in the Czech Republic) based their claim for a payment of amount of money on the agreement by which they provided the consultancy for the defendant (domiciled in Austria) who had the interest to acquire the majority interest in a company. However, the defendant did not pay this amount. The court of first instance assessed the matter notably from the perspective of the capacity to act on behalf of the defendant and whether a contractual relationship between the parties of the case came into existence. The court considered that it was not established that the parties concluded the contract and therefore the Regulation (EC) No 44/2001 on jurisdiction and the recognition and enforcement of judgments in civil and commercial matters (“Brussels I Regulation”) was not applicable. It concluded that the Czech courts do not have the jurisdiction and discontinued the proceedings. The appellate court confirmed the decision and stressed that it was not established that the defendant made a direct, though not binding, demand towards (each of) the applicants.
The Supreme Court firstly stressed that the application of the rule on the international jurisdiction in Art. 5 (1) of the Brussels I Regulation is not precluded if there is a doubt whether a contract was concluded. The application of Article 5 (1) presumes the existence of a freely accepted legal obligation by one person towards the other person. Therefore, the lower courts had obligation to deal with the question whether free acceptance of the obligation occurred between the parties of the case. The Supreme Court established that if a court has relevant information at its disposal, it is not necessary to carry out detailed evidence already in the phase of the assessment of the international jurisdiction in the same extent as is the court when it decides on the merits of the case. The lower courts were obliged to take into consideration all the facts on which the applicants based their conviction that the Czech courts have international jurisdiction and to base their reasoning on those facts unless they were rebutted by the defendant. They were not supposed to deal with the validity of the contract in the light of the capacity of particular person to act in the name of the defendant but it sufficed to consider the arguments of the applicants about the interest of the defendant to acquire the majority interest in the company and the obligation of the applicants to provide the defendant with services necessary to realise his intentions. It was also necessary to take into account the conduct of persons about who the applicants could rightfully presume that they act in the name of the defendant. The lower courts, by the assessment of the information, were supposed to answer a question whether the applicants assumed the obligation against the defendant and whether he or she, although implicitly, accepted it. If the appellate court did not proceed in such a manner, the legal assessment of the question of international jurisdiction was incomplete and thus incorrect. The Supreme Court recalled, in the end, that if a court comes to a conclusion of the absence of conditions for the international jurisdiction of the Czech courts in the meaning of Article 5 (1) of the Regulation, the previous case-law of the Supreme Court does not rule out the application of Article 5 (3) of the Regulation. The term “concurrent applicability”, used by the Supreme Court in its previous case-law, points at the fact that it is not possible to infer international jurisdiction from both provisions at the same time because they exclude each other in their applicability.